Project at a Glance

Project Name

Bangalore Vijayawada Expressway

Other Name

NH-544G, or Bangalore-Kadapa-Vijayawada (BKV) Expressway

Project Sector

Infrastructure

Project Type

Both Greenfield & Brownfield

Project Status

Under Construction

Project Cost

INR 19,320 crore (approximately USD 2.31 billion)

Construction Start Date

11 March 2024

Construction End Date

2026 (Expected)

Project Developer

National Highway Authority of India (NHAI)

Starting Point 

Kodikonda in Andhra Pradesh

Ending Point 

Addanki, Andhra Pradesh

Total Expressway Length

624 km

Under-Construction Expressway Length

518 km

Right-of-way

100 m

Lanes

6-lane

Project Overview

The Bangalore Vijayawada Expressway is an infrastructure project developed by the National Highway Authority of India (NHAI). It is a 624 km-long expressway, of which 64% will be greenfield construction, and the remaining 36% will be brownfield construction.

This six-lane, access-controlled, under-construction expressway will cut travel time to 6 hours once completed (expected by 2026). It is also known as the NH-544G, or Bangalore-Kadapa-Vijayawada (BKV) Expressway, as it passes through Kadapa.

The expressway will pass through key districts of Andhra Pradesh and Karnataka. It starts from Kodikonda in Andhra Pradesh, connecting Bangalore, and ends at Vijayawada. The expressway will also connect to major national highways, such as National Highway-44 and National Highway-16.

Upon full completion, the expressway is expected to improve connectivity for Prakasam’s agricultural and industrial belts, easing the faster movement of farm products to markets of Vijayawada, Bangalore, and ports on the east coast.

Project Background

The Bangalore Vijayawada Expressway (also known as the BKV Expressway) is a project developed by NHAI under the Bharatmala Pariyojana Phase II. In 2021, the Government of Andhra Pradesh submitted a detailed proposal to the Union Ministry of Road Transport and Highways (MoRTH) for an expressway connecting Bangalore to Vijayawada via Kadapa.

The Government of India approved the proposal in August 2021. The initial plan was to construct a 514 km-long expressway, with 404 km as a new greenfield section primarily in Andhra Pradesh, and the remaining 110 km utilizing upgrades to existing highways.

The project was revised again in September 2022 by the National Highway Authority of India (NHAI). It declared the expressway as NH-544G. Now, the new length of the expressway is 624 km, with 518 km being a greenfield stretch.

Tenders for the project were invited in September 2022 under the Hybrid Annuity Model (HAM), where contractors receive annuity payments post-completion. Land acquisition commenced in December 2022, with NHAI acquiring over 4,000 hectares. Prime Minister Narendra Modi laid the foundation stone for the project on 11 March 2024.

Bangalore Vijayawada Expressway Status & Completion Date

As of January 2025, the Bangalore Vijayawada Expressway is an under-construction project expected to be completed in 2026. Civil works, including earthworks, embankment construction, bridges, flyovers, and asphalt surfacing, are advancing rapidly, particularly in Andhra Pradesh districts such as Kurnool, Kadapa, Prakasam, and Guntur. Divided into 14 packages, none of them is operational yet.

40+ reviews

Find the Latest Road Infrastructure Projects In India

Gain exclusive access to our industry-leading database of infrastructure project opportunities with detailed project timelines and stakeholder information.

​Collect Your Free Leads Here!

No credit cardUp-to-date coverage

Joined by 750+ industry professionals last month

Bangalore Vijayawada Expressway Route Map

Bangalore Vijayawada Expressway Route Map

Bangalore Vijayawada Expressway Route

The Bangalore Vijayawada Expressway connects Bangalore to Vijayawada, covering two states, Karnataka and Andhra Pradesh. Along the route, the expressway passes through 11 districts - 3 in Karnataka and 8 in Andhra Pradesh.

It will start from NH44 at Kodikonda in Andhra Pradesh. While passing through the Rayalaseema Region, it connects to Bangalore. The expressway ends at NH16 in Addanki, Andhra Pradesh, connecting to Vijayawada.

Bangalore Vijayawada Expressway: Brownfield & Greenfield Sections

Type

Starting Point

Ending point

Brownfield

Bangalore

Kodikonda

Greenfield

Kodikonda on NH44

Addanki 

Brownfield

Addanki

Vijayawada on NH16


 Bangalore Vijayawada Expressway: Districts Covered

State

District

Karnataka

Bangalore

Chikkaballapur

Devanahalli (in the Bangalore rural district)

Andhra Pradesh

Sri Sathya Sai (Starts near Kodikonda border area)

Anantapur (parts near Kurnool overlap)

Kadapa (YSR Kadapa, including Pulivendula, Yerraguntla)

Kurnool (Major section in Rayalaseema alignment)

Prakasam (Major stretch including Podili, Kanigiri, Addanki)

Bapatla (Near Addanki Area)

Guntur (Mangalagiri, Amaravati Area)

Vijayawada (End Point)


Bangalore Vijayawada Expressway Cost

The total estimated cost for the Bangalore Vijayawada Expressway is INR 19,320 crore (approximately USD 2.31 billion). It covers the cost of all 14 packages, including earthworks, structures (bridges and flyovers), pavement, and right-of-way acquisition (100m wide).

The expressway is constructed under the Hybrid Annuity Model (HAM), where the project cost is funded by NHAI (40%) and the Andhra Pradesh Government (60%).

Project Timeline

Year

Event

2026

Expected completion of the project

6 January 2026

NHAI achieved two Guinness World Records

11 March 2024

Prime Minister Narendra Modi laid the foundation stone for the project

March 2023

All 14 packages awarded to contractors

September 2022

Tenders invited for the project

2022

NHAI revised the project and declared the expressway as NH-544G

August 2021

The Government of India approved the project

2021

The Government of Andhra Pradesh submitted a detailed proposal to the Union Ministry of Road Transport and Highways (MoRTH)

40+ reviews

Find the Latest Road Infrastructure Projects In India

Gain exclusive access to our industry-leading database of infrastructure project opportunities with detailed project timelines and stakeholder information.

​Collect Your Free Leads Here!

No credit cardUp-to-date coverage

Joined by 750+ industry professionals last month

Project Scope

The project scope of the Bangalore Vijayawada Expressway is discussed below:

  • Links manufacturing hubs: The expressway covers Karnataka and Andhra Pradesh, connecting tech/manufacturing hubs to ports and agriculture belts.

  • Expressway Speed: The Bangalore Vijayawada Expressway is designed with 100 m right-of-way and enjoys a maximum speed of 120 km/hr.

  • Greenfield & Brownfield Stretch: The expressway is both greenfield (64%) and brownfield (36%).

  • National Highway Integration: The expressway will also connect to major national highways, such as National Highway-44 and National Highway-16.

  • Infrastructure: It comprises bridges, flyovers, culverts, and interchanges to bypass urban congestion in areas such as Kadapa, Guntur, Prakasam, and Addanki.

Bangalore Vijayawada Expressway Packages & Contractors

S.NO

Packages

Contractors

1

Kodur to Vanavolu

Dilip Buildcon

2

Vanavolu to Vankarakunta

Vankarakunta to Odulapalle

Raj Path Infracon

3

Odulapalle to Nallacheruvupali

Dilip Buildcon

4

Nallacheruvupali to Yerragudipadu

Megha Engineering (MEIL)

5

Yerragudipadu to Audireddipalle

Megha Engineering (MEIL)

6

Audireddipalle to Mallapalle

Dilip Buildcon

7

Mallapalle to Kavulakuntla

Megha Engineering (MEIL)

8

Kavulakuntla to Narayanpet

Max Infra - Bekem Infra

9

Narayanpet to Chandrasekharpuram

Megha Engineering (MEIL)

10

Chandrasekharpuram to Polavaram

Megha Engineering (MEIL)

11

Polavaram to Marripudi

Megha Engineering (MEIL)

12

Marripudi to Somavarappadu

KNR Constructions

13

Somavarappadu to Muppavaram

Megha Engineering (MEIL)


Bangalore Vijayawada Expressway Investors

Investors

Share

National Highway Authority of India

40%

Andhra Pradesh Government

60%

Bangalore Vijayawada Expressway Latest News

The National Highway Authority of India (NHAI) achieved a major milestone under the Bangalore Vijayawada Expressway Construction project. On 6 January 2026, NHAI achieved two Guinness World Records for laying Bituminous Concrete on the Vanavolu–Vankarakunta section of the 6-lane Bengaluru–Kadapa–Vijayawada Economic Corridor.

It includes the 28.95 km-long distance lane of Bituminous Concrete laid continuously within 24 hours, and 10,675 metric tonnes, the highest quantity of Bituminous Concrete constantly laid within 24 hours.

Both these awards are the first-ever Guinness World Records in their respective categories. The achievement spotlights India’s commitment to building world-class National Highway infrastructure.

Benefits

The following are the benefits of the project:

  • Reduce Travel Time: Once fully operational, the expressway will halve travel time. Currently, it takes approximately 12 hours to travel. Upon operation, the 624 km long distance will be covered in just 6 hours.

  • Reduce Traffic: The expressway will replace the highly congested NH44 and NH16 routes, which are vulnerable to traffic congestion, signal delays, and monsoon damage.​ Overall, reducing traffic and ensuring efficient transport.

  • Boosts Trade: It boosts trade, logistics, and supply chains between Bangalore’s manufacturing hubs and Vijayawada's ports/agriculture.

  • Reduce Logistics Costs: The expressway will significantly reduce logistics costs by enabling faster delivery of goods.

  • Improves South India Integration: The expressway ultimately improves South India Integration, including links to eastern ports and NH-16.

Conclusion

The Bangalore Vijayawada Expressway is an under-construction project developed by NHAI as a brownfield and greenfield stretch. It is a 624 km-long, six-lane expressway expected to be completed by 2026.

Developed under the Bharatmala Pariyojana Phase II, the NHAI achieved two Guinness World Records for laying Bituminous Concrete. This achievement marks India’s commitment to building world-class National Highway infrastructure.

It implements strong economic growth across 11 districts, spurring investments in warehousing, MSMEs, and real estate while reducing regional logistics costs. Overall, it improves South India's integration, enhances trade efficiency, and supports national goals for faster, greener mobility.

Track the Latest Infrastructure Projects in India for Business Opportunities.

Subscribe to our upcoming and ongoing infrastructure projects in India to access reliable, high-quality insights on forthcoming and completed infrastructure projects across the country.


Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.


Start a free demo to take your business to the next level.

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile