Last Updated on 24th June 2024
RWE has made an investment decision on the 1.6 GW Nordseecluster offshore wind farms in Germany. The Nordseecluster project is about 50 kilometers north of the island of Juist, situated in the German North Sea. The project is implemented in two phases: Nordsee Cluster A and B.
The construction of Nordseecluster A, with a capacity of 660 MW, will commence in 2025, with full commissioning planned for the beginning of 2027. The construction of Nordseecluster B, with a capacity of 900 MW, is expected to begin in 2027, with full commissioning to occur at the beginning of 2029. Additionally, Vestas will provide 104 wind turbines for the Nordsee cluster, with cluster A having 44 and cluster B having 60, respectively, generating around 6.5 TWh of electricity per year.
Sven Utermöhlen, CEO of RWE Offshore Wind, said, “Our portfolio already includes six offshore wind farms off Germany’s coastlines. The Nordseecluster will add two more. This sends a good signal for the energy transition in Germany and RWE.”
RWE does not have to make lease payments to the German Federal Network Agency (Bundesnetzagentur) for the Nordseecluster sites. The cluster size will provide synergy effects for RWE in the construction and subsequent operation of the offshore wind farms in Germany.
The generated renewable energy from offshore wind farms will support its industrial customers on the path to decarbonization with customized energy solutions. These customers increasingly include operators of AI data centers.
The company has developed around 19 offshore wind farms worldwide, with six off the German coast. RWE has set itself the goal of tripling its global offshore wind capacity from 3.3 GW to 10 GW in 2030.
Project Location: Map Source: RWE
The Nordseecluster combines wind farm sites in the eastern part of the German North Sea into a 1.6 GW offshore wind project. The combination of those sites opens up unique economies of scale. Some key components have already been manufactured for Nordseecluster A. The two phases are divided into 4 clusters: NC1, NC2, NC3, and NC4.
Project Phase |
Cluster |
Capacity |
Nordsea A |
NC1 |
225 MW |
Nordsea A |
NC2 |
435 MW |
Nordsea B |
NC3 |
420 MW |
Nordsea B |
NC4 |
480 MW |
Read: Dominion Energy Started the Construction of Largest Offshore Wind project in USA
Subscribe to upcoming and ongoing Offshore Wind projects and tenders database in Germany to get access to reliable and high-quality insights on upcoming, in-progress, and completed offshore wind projects in Germany.
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Start a free demo to take your business to the next level!